Bill S3414A-2011

Authorizes contractors or subcontractors to postpone commencing work until proposed changes exceeding 10% of the original contract are approved by the public owner

Authorizes contractors or subcontractors to postpone commencing work until proposed changes exceeding 10% of the original contract have been approved by the public owner.

Details

Actions

  • Apr 18, 2012: referred to governmental operations
  • Apr 18, 2012: DELIVERED TO ASSEMBLY
  • Apr 18, 2012: PASSED SENATE
  • Mar 22, 2012: ADVANCED TO THIRD READING
  • Mar 21, 2012: 2ND REPORT CAL.
  • Mar 20, 2012: 1ST REPORT CAL.386
  • Jan 4, 2012: REFERRED TO FINANCE
  • Jan 4, 2012: returned to senate
  • Jan 4, 2012: died in assembly
  • Jun 13, 2011: referred to governmental operations
  • Jun 13, 2011: DELIVERED TO ASSEMBLY
  • Jun 13, 2011: PASSED SENATE
  • Jun 6, 2011: AMENDED ON THIRD READING 3414A
  • Jun 1, 2011: ADVANCED TO THIRD READING
  • May 25, 2011: 2ND REPORT CAL.
  • May 24, 2011: 1ST REPORT CAL.852
  • Feb 18, 2011: REFERRED TO FINANCE

Votes

Memo

BILL NUMBER:S3414A

TITLE OF BILL: An act to amend the state finance law and the general municipal law, in relation to contract change orders

PURPOSE OR GENERAL IDEA OF BILL: This bill adds a new subdivision 5 to section 139-f of the state finance law and a new subsection 4 to section 106-b of the general municipal law to provide that when unapproved change orders exceed 10% of the original contract, the contractor or subcontractor shall not be required to proceed with such change order work until it is approved by the owner.

SUMMARY OF SPECIFIC PROVISIONS: A new subdivision 5 of Section 139-f of the state finance law provides if at any time during the construction period, the total cost of all unapproved change orders, change directives and contract amendments exceed ten (10%) percent of the original contract or subcontract, the contractor or subcontractor, as the case may be, shall not be required to commence or continue such work until the proposed changes or amendments have been approved by the public owner.

A new subdivision 4 of the general municipal law provides if at any time during the construction period, the total cost of all unapproved change orders, change directives and contract amendments exceed ten (10%) percent of the original contract or subcontract, the contractor or subcontractor, as the case may be, shall not be required to commence or continue such work until the proposed changes or amendments have been approved by the public owner.

JUSTIFICATION: Contractors who are compelled to continue work on change orders while other change orders completed or being worked on have yet to be approved are placed at a disadvantage and risk of no-payment. This bill addresses this issue.

The State of Connecticut enacted similar legislation in 2009.

PRIOR LEGISLATIVE HISTORY: New bill.

FISCAL IMPLICATIONS: None.

EFFECTIVE DATE: This act shall take effect immediately and shall apply to all contracts executed on and after the date of this act.


Text

STATE OF NEW YORK ________________________________________________________________________ S. 3414--A A. 5412--A Cal. No. 852 2011-2012 Regular Sessions S E N A T E - A S S E M B L Y February 18, 2011 ___________
IN SENATE -- Introduced by Sen. KLEIN -- read twice and ordered printed, and when printed to be committed to the Committee on Finance -- reported favorably from said committee, ordered to first and second report, ordered to a third reading, amended and ordered reprinted, retaining its place in the order of third reading IN ASSEMBLY -- Introduced by M. of A. CUSICK, ROBINSON -- Multi-Spon- sored by -- M. of A. P. RIVERA -- read once and referred to the Committee on Governmental Operations -- committee discharged, bill amended, ordered reprinted as amended and recommitted to said commit- tee AN ACT to amend the state finance law and the general municipal law, in relation to contract change orders THE PEOPLE OF THE STATE OF NEW YORK, REPRESENTED IN SENATE AND ASSEM- BLY, DO ENACT AS FOLLOWS: Section 1. Section 139-f of the state finance law is amended by adding a new subdivision 5 to read as follows: 5. IF AT ANY TIME DURING THE CONSTRUCTION PERIOD, THE TOTAL COST OF ALL UNAPPROVED CHANGE ORDERS, CHANGE DIRECTIVES AND CONTRACT AMENDMENTS EXCEED TEN PERCENT OF THE ORIGINAL CONTRACT OR SUBCONTRACT, THE CONTRAC- TOR IN THE CASE OF THE ORIGINAL CONTRACT OR SUBCONTRACT, OR SUBCONTRAC- TOR IN THE CASE OF THE SUBCONTRACT, SHALL NOT BE REQUIRED TO COMMENCE OR CONTINUE SUCH WORK UNTIL THE PROPOSED CHANGES OR AMENDMENTS HAVE BEEN APPROVED BY THE PUBLIC OWNER. S 2. Section 106-b of the general municipal law is amended by adding a new subdivision 4 to read as follows: 4. IF AT ANY TIME DURING THE CONSTRUCTION PERIOD, THE TOTAL COST OF ALL UNAPPROVED CHANGE ORDERS, CHANGE DIRECTIVES AND CONTRACT AMENDMENTS EXCEED TEN PERCENT OF THE ORIGINAL CONTRACT OR SUBCONTRACT, THE CONTRAC- TOR IN THE CASE OF THE ORIGINAL CONTRACT OR SUBCONTRACT, OR SUBCONTRAC- TOR IN THE CASE OF THE SUBCONTRACT, SHALL NOT BE REQUIRED TO COMMENCE OR
CONTINUE SUCH WORK UNTIL THE PROPOSED CHANGES OR AMENDMENTS HAVE BEEN APPROVED BY THE PUBLIC OWNER. S 3. This act shall take effect immediately and shall apply to all contracts executed on and after such date.

Comments

Open Legislation comments facilitate discussion of New York State legislation. All comments are subject to moderation. Comments deemed off-topic, commercial, campaign-related, self-promotional; or that contain profanity or hate speech; or that link to sites outside of the nysenate.gov domain are not permitted, and will not be published. Comment moderation is generally performed Monday through Friday.

By contributing or voting you agree to the Terms of Participation and verify you are over 13.

Discuss!

blog comments powered by Disqus